Liam O’Connor
10 February 2026
Inspected settlement issue along the service trench. Found poorly compacted backfill and applied a temporary fix. A quote for further work was initiated while invoicing for today's visit.
Checked the excavation status and found issues with backfill.
Reviewed drainage runs, no issues found.
Inspected foundation trenches, no issues found.
To approve the work required for the re-compaction of the trench.
| Item | Quantity | Priority |
|---|---|---|
| Re-compact trench with whacker, add Type 1 stone and geotextile | 1 | Medium |
Call-out service and labour completed today.
| Item | Quantity |
|---|---|
| Call-out and 1 hour labour with geotextile offcut used | 1 |