Alex Johnson
10 February 2026
Inspection and temporary repair of junction box due to water ingress.
Checked cabling infrastructure and found it okay.
Found corroded junction box and water ingress; remade joint with gel crimps.
Checked signal quality and found it okay.
Replacing corroded junction box and running new cable.
| Item | Quantity | Priority |
|---|---|---|
| External junction box replacement | 1 | Medium |
| New drop cable installation | 1 | Medium |
Call-out and labour completed, materials used for temporary fix.
| Item | Quantity |
|---|---|
| Call-out charge | 1 |
| Labour charge for visit | 1 |
| Gel-filled crimps for temporary joint | 1 |