Sophie Martin
10 February 2026
Inspection conducted on the blown patch on the ceiling with a temporary fix applied. Further work scheduled after quote approval.
Sophie to monitor over the next week for changes.
Checked and addressed a blown patch.
Cut out loose skim and sealed edges.
work needed to be completed after approval
| Item | Quantity | Priority |
|---|---|---|
| Hack off and re-skim 2m² around crack, tape and fill adjacent joint lines | 2 | Medium |
services rendered during visit
| Item | Quantity |
|---|---|
| Call-out fee and 1 hour of labour | 1 |
| Bonding coat for patch stabilization | 1 |